| S/No. |
Client |
Description |
Date |
| 51 |
Jurong Engineering Limited |
Repair water leakage at tunnel end wall joint
for Jurong Island (opposite Continental Building) Project |
May 2003 |
| 52 |
In-Sign Ltd |
Repair cracks on beam and soffit using Unifor Crack Injection System at Tuen Mun Town Plaza I Carpark, Hong Kong (Demo) |
Aug 2003 |
| 53 |
Sato Kogyo Co., Ltd |
Repair water leakage on structural cracks on retaining wall using Unifor Underwater Epoxy Grouting Method at Viaduct from Airport Road
to Tampines Ave 10 Project |
Sep 2003 |
| 54 |
Hyundai Engineering & Construction Co., Ltd |
Repair cracks on Level 2 Deck using Unifor Crack Injection System for
MRT NEL C701 Project |
Sep 2003 |
| 55 |
Hyundai - Chung Lin J.V. |
Repair structural cracks using Unifor Underwater Epoxy Grouting Method for Taiwan High Speed Railway System Contract 240 Project |
Oct 2003 - 2006 |
| 56 |
Jungtap Construction Co., Ltd |
Repair water leakage on structural cracks inside tunnel using Unifor Underwater Epoxy Grouting Method for Taiwan High Speed
Railway System Contract 230-B Project |
Oct 2003 - 2006 |
| 57 |
Kumagai-Sembawang-Mitsui J.V. |
Repair water leakage in ring segment tunnel,
Cover & Cover Tunnel and Station using Unifor Underwater Epoxy Grouting Method
for MRT NEL C705 Project |
Oct 2003 - Jul 2004 |
| 58 |
Hyundai Engineering & Construction Co., Ltd |
Repair cracks on R.C. floor slab Unifor Crack Injection System at KUNOP Oil Refinery Project (Demo) in Kuwait |
Nov 2003 - 2005 |
| 59 |
Lum Chang Building Contractors Pte Ltd |
Repair water leakage on construction joint between beam and slab using Unifor Underwater Epoxy Grouting Method at Blk 3
Casabella Condominium |
Nov 2003 |
| 60 |
HP Construction & Engineering Pte Ltd |
Repair cracks on R.C. roof slab soffit using Unifor Underwater Epoxy Grouting Method at No. 10 Depot Walk |
Dec 2003 |
| 61 |
Hyundai Engineering & Construction Co., Ltd |
Repair water leakage at station using Unifor Underwater Epoxy Grouting Method for MRT NEL C706 Project |
Dec 2003 - Jan 2004 |
| 62 |
Obayashi-McConnell Dowell J.V. |
Grout socket hole on segment inside tunnel with grout cap and repair
water leakage between segment to segment inside tunnel and repair cracks on tunnel wall
using Unifor Underwater Epoxy Grouting Method at Senoko-Gambas Cable East Tunnel Project |
Feb 2004 - Feb 2005 |
| 63 |
Kumagai-SembCorp J.V. |
Repair water leakage at interface(tunnel & Station) and baggage tunnel for MRT CAL C504 Project |
Mar 2004 - Jul 2004 |
| 64 |
Shimizu Corporation |
Repair water leakage on construction joint on R.C. wall using Unifor Underwater Epoxy Grouting Method for
Grange Residences Project |
Mar 2004 |
| 65 |
B-Gold Interior Design & Construction Pte Ltd |
Repair water leakage on construction joint for MediaCorp Project |
Mar 2004 - May 2004 |
| 66 |
Tekken/Union/SP J.V. |
Repair water leakage on track floor of NEL for MRT NEL C716 Project |
Apr 2004 - Jul 2004 |
| 67 |
Shimizu Coporation |
Repair bearing pad on pedestrain link bridge using UF Grout and widen beam on
basement carpark for Caribbean Condominium Project |
Apr 2004 - Jun 2004 |
| 68 |
Eac Enterprise Pte Ltd |
Repair cracks on hollow screed on void deck using Unifor Crack Injection System (Epoxy Grouting)
at lengkong Tiga for Kembangan Estate Project |
Apr 2004 - Jul 2004 |
| 69 |
Eac Enterprise Pte Ltd |
Repair cracks on hollow screed on staircase walkway using Unifor Crack Injection System (Epoxy
Grouting) for Tampines H.D.B. Project |
May 2004 - Sep 2004 |
| 70 |
SembCorp Engineers and Constructors Pte Ltd |
Repair damaged R.C. concrete and waterproofing membrane on south bound external wall for
ECP Contract 421 Project |
Jun 2004 - 2005 |
| 71 |
Shanghai Tunnel Engineering Co., Ltd |
Repair water leakage on joint segment inside tunnel for CCL MRT C822 Project |
Jun 2004 |
| 72 |
Dong-A Geological Engineering Co., Ltd |
Grout water leakage on joint inside tunnel lining Unifor
Underwater Epoxy Grouting Method for DTSS Kim Chuan Link Sewers Contract 01 Project |
Jul 2004 |
| 73 |
Eac Enterprise Pte Ltd |
Grout cracks on hollow screed on void deck using Unifor Crack Injection System (Epoxy Grouting)
for Hougang N5 Estate Project |
Jul 2004 - Sep 2004 |
| 74 |
China Civil Engrg Constn Corpn (Grp) S'pore Branch |
Repair honeycomb on R.C. wall for MRT Circle Line C822 Project |
Oct 2004 |
| 75 |
Lum Chang Building Contractors Pte Ltd |
Repair dry cracks on R.C. wall & soffit using Unifor Crack Injection System
(Epoxy Grouting), repair water leakage in Station and Cut & Cover Tunnel using Unifor Underwater
Epoxy Grouting Method and seal gap between R.C. wall and slab for MRT Circle Line Stage I C824 Project |
Oct 2004 - Sep 2005 |